Indemnification and limitation of liability
Requirement of financial protection for licensees
Each license issued under section 2133 or 2134 of this title and each construction permit issued under section 2235 of this title shall, and each license issued under section 2073, 2093, or 2111 of this title may, for the public purposes cited in section 2012(i) of this title, have as a condition of the license a requirement that the licensee have and maintain financial protection of such type and in such amounts as the Nuclear Regulatory Commission (in this section referred to as the “Commission”) in the exercise of its licensing and regulatory authority and responsibility shall require in accordance with subsection (b) to cover public liability claims. Whenever such financial protection is required, it may be a further condition of the license that the licensee execute and maintain an indemnification agreement in accordance with subsection (c). The Commission may require, as a further condition of issuing a license, that an applicant waive any immunity from public liability conferred by Federal or State law.
Amount and type of financial protection for licensees
The Commission may, on a case by case basis, assess annual deferred premium amounts less than the standard annual deferred premium amount assessed under paragraph (1)—
In the event that the funds available to pay valid claims in any year are insufficient as a result of the limitation on the amount of deferred premiums that may be required of a licensee in any year under paragraph (1) or (2), or the Commission is required to make reinsurance or guaranteed payments under paragraph (3), the Commission shall, in order to advance the necessary funds—
Indemnification of licensees by Nuclear Regulatory Commission
The Commission shall, with respect to licenses issued between , and , for which it requires financial protection of less than $560,000,000, agree to indemnify and hold harmless the licensee and other persons indemnified, as their interest may appear, from public liability arising from nuclear incidents which is in excess of the level of financial protection required of the licensee. The aggregate indemnity for all persons indemnified in connection with each nuclear incident shall not exceed $500,000,000 excluding costs of investigating and settling claims and defending suits for damage: Provided, however, That this amount of indemnity shall be reduced by the amount that the financial protection required shall exceed $60,000,000. Such a contract of indemnification shall cover public liability arising out of or in connection with the licensed activity. With respect to any production or utilization facility for which a construction permit is issued between , and , the requirements of this subsection shall apply to any license issued for such facility subsequent to .
Indemnification of contractors by Department of Energy
In an agreement of indemnification entered into under paragraph (1), the Secretary—
Limitation on aggregate public liability
The aggregate public liability for a single nuclear incident of persons indemnified, including such legal costs as are authorized to be paid under subsection (o)(1)(D), shall not exceed—
in the case of all other licensees of the Commission required to maintain financial protection under this section—
Collection of fees by Nuclear Regulatory Commission
The Commission or the Secretary, as appropriate, is authorized to collect a fee from all persons with whom an indemnification agreement is executed under this section. This fee shall be $30 per year per thousand kilowatts of thermal energy capacity for facilities licensed under section 2133 of this title: Provided, That the Commission or the Secretary, as appropriate, is authorized to reduce the fee for such facilities in reasonable relation to increases in financial protection required above a level of $60,000,000. For facilities licensed under section 2134 of this title, and for construction permits under section 2235 of this title, the Commission is authorized to reduce the fee set forth above. The Commission shall establish criteria in writing for determination of the fee for facilities licensed under section 2134 of this title, taking into consideration such factors as (1) the type, size, and location of facility involved, and other factors pertaining to the hazard, and (2) the nature and purpose of the facility. For other licenses, the Commission shall collect such nominal fees as it deems appropriate. No fee under this subsection shall be less than $100 per year.
Use of services of private insurers
In administering the provisions of this section, the Commission or the Secretary, as appropriate, shall use, to the maximum extent practicable, the facilities and services of private insurance organizations, and the Commission or the Secretary, as appropriate, may contract to pay a reasonable compensation for such services. Any contract made under the provisions of this subsection may be made without regard to the provisions of section 6101 of title 41 upon a showing by the Commission or the Secretary, as appropriate, that advertising is not reasonably practicable and advance payments may be made.
Conditions of agreements of indemnification
The agreement of indemnification may contain such terms as the Commission or the Secretary, as appropriate, deems appropriate to carry out the purposes of this section. Such agreement shall provide that, when the Commission or the Secretary, as appropriate, makes a determination that the United States will probably be required to make indemnity payments under this section, the Commission or the Secretary, as appropriate, shall collaborate with any person indemnified and may approve the payment of any claim under the agreement of indemnification, appear through the Attorney General on behalf of the person indemnified, take charge of such action, and settle or defend any such action. The Commission or the Secretary, as appropriate, shall have final authority on behalf of the United States to settle or approve the settlement of any such claim on a fair and reasonable basis with due regard for the purposes of this chapter. Such settlement shall not include expenses in connection with the claim incurred by the person indemnified.
Compensation plans
After any nuclear incident involving damages that are likely to exceed the applicable amount of aggregate public liability under subparagraph (A), (B), or (C) of subsection (e)(1), the Secretary or the Commisison,1
as appropriate, shall—Not later than 90 days after any determination by a court, pursuant to subsection (o), that the public liability from a single nuclear incident may exceed the applicable amount of aggregate public liability under subparagraph (A), (B), or (C) of subsection (e)(1) the President shall submit to the Congress—
For the purpose of paragraph (4) of this subsection—
This paragraph is enacted—
Contracts in advance of appropriations
In administering the provisions of this section, the Commission or the Secretary, as appropriate, may make contracts in advance of appropriations and incur obligations without regard to sections 1341, 1342, 1349, 1350, and 1351, and subchapter II of chapter 15, of title 31.
Exemption from financial protection requirement for nonprofit educational institutions
With respect to any license issued pursuant to section 2073, 2093, 2111, 2134(a), or 2134(c) of this title, for the conduct of educational activities to a person found by the Commission to be a nonprofit educational institution, the Commission shall exempt such licensee from the financial protection requirement of subsection (a). With respect to licenses issued between , and , for which the Commission grants such exemption:
Presidential commission on catastrophic nuclear accidents
The study commission shall consist of not less than 7 and not more than 11 members, who—
The study commission shall conduct a comprehensive study of appropriate means of fully compensating victims of a catastrophic nuclear accident that exceeds the amount of aggregate public liability under subsection (e)(1), and shall submit to the Congress a final report setting forth—
Coordinated procedures for prompt settlement of claims and emergency assistance
The Commission or the Secretary, as appropriate, is authorized to enter into agreements with other indemnitors to establish coordinated procedures for the prompt handling, investigation, and settlement of claims for public liability. The Commission or the Secretary, as appropriate, and other indemnitors may make payments to, or for the aid of, claimants for the purpose of providing immediate assistance following a nuclear incident. Any funds appropriated to the Commission or the Secretary, as appropriate, shall be available for such payments. Such payments may be made without securing releases, shall not constitute an admission of the liability of any person indemnified or of any indemnitor, and shall operate as a satisfaction to the extent thereof of any final settlement or judgment.
Waiver of defenses and judicial procedures
With respect to any extraordinary nuclear occurrence to which an insurance policy or contract furnished as proof of financial protection or an indemnity agreement applies and which—
Following any nuclear incident, the chief judge of the United States district court having jurisdiction under paragraph (2) with respect to public liability actions (or the judicial council of the judicial circuit in which the nuclear incident occurs) may appoint a special caseload management panel (in this paragraph referred to as the “management panel”) to coordinate and assign (but not necessarily hear themselves) cases arising out of the nuclear incident, if—
It shall be the function of each management panel—
Plan for distribution of funds
Whenever the United States district court in the district where a nuclear incident occurs, or the United States District Court for the District of Columbia in case of a nuclear incident occurring outside the United States, determines upon the petition of any indemnitor or other interested person that public liability from a single nuclear incident may exceed the limit of liability under the applicable limit of liability under subparagraph (A), (B), or (C) of subsection (e)(1):
A court may authorize the payment of legal costs under paragraph (1)(D) only if the person requesting such payment has—
demonstrated to the court—
that such person has—
Reports to Congress
The Commission and the Secretary shall submit to the Congress by , detailed reports concerning the need for continuation or modification of the provisions of this section, taking into account the condition of the nuclear industry, availability of private insurance, and the state of knowledge concerning nuclear safety at that time, among other relevant factors, and shall include recommendations as to the repeal or modification of any of the provisions of this section.
Limitation on awarding of precautionary evacuation costs
No court may award costs of a precautionary evacuation unless such costs constitute a public liability.
Limitation on liability of lessors
No person under a bona fide lease of any utilization or production facility (or part thereof or undivided interest therein) shall be liable by reason of an interest as lessor of such production or utilization facility, for any legal liability arising out of or resulting from a nuclear incident resulting from such facility, unless such facility is in the actual possession and control of such person at the time of the nuclear incident giving rise to such legal liability.
Limitation on punitive damages
No court may award punitive damages in any action with respect to a nuclear incident or precautionary evacuation against a person on behalf of whom the United States is obligated to make payments under an agreement of indemnification covering such incident or evacuation.
Inflation adjustment
The Commission shall adjust the amount of the maximum total and annual standard deferred premium under subsection (b)(1) not less than once during each 5-year period following , in accordance with the aggregate percentage change in the Consumer Price Index since—
The Secretary shall adjust the amount of indemnification provided under an agreement of indemnification under subsection (d) not less than once during each 5-year period following , in accordance with the aggregate percentage change in the Consumer Price Index since—